(1) The Authority and the Applicant must execute a grant contract prior to disbursal of grant funds.

(2) Documentation of project costs incurred by entity must be submitted to the Authority prior to disbursal of funds.

(3) Disbursal of grant funds to entity will be made on the schedule determined by the Authority.

(4) Prior to final disbursement, the Authority will review and evaluate all documents produced as a result of the project, and determine how closely the project delivered the outcome anticipated in the application.