Department of Energy
Energy Facility Siting Council - Chapter 345
Division 29
NOTICE OF VIOLATION, CIVIL PENALTIES, REVOCATION OR SUSPENSION
345-029-0040
Response to Notice of Violation
In the written response required by OAR 345-029-0020(2)(c), the responsible party must include, as a minimum, the following:
(1) Admission or denial of the violation;
(2) If the responsible party admits the violation and can determine suitable corrective action:
(a) The corrective action taken, and results achieved;
(b) Corrective action that the responsible party plans to take to minimize the possibility of recurrence; and
(c) The date by which the responsible party expects to achieve full compliance; and
(3) If the responsible party admits the violation and cannot determine suitable corrective actions within the 30-day or other time period specified in the notice of violation, a preliminary response that includes a date by which the responsible party will submit a final response that includes all information described in section (2).
Statutory/Other Authority: ORS 469.470
Statutes/Other Implemented: ORS 469.085, 469.440 & 469.992
History:
EFSC 1-2021, amend filed 02/26/2021, effective 02/26/2021
EFSC 2-1999, f. & cert. ef. 4-14-99
EFSC 1-1995, f. & cert. ef. 5-15-95
EFSC 5-1994, f. & cert. ef. 11-30-94