Oregon Secretary of State

State Board of Architect Examiners

Chapter 806

Division 10
GENERAL

806-010-0050
Observation

(1) Construction phase services that constitute the practice of architecture include but are not limited to:

(a) Clarification and modification of technical submissions during the construction phase; and

(b) Observing the construction site through substantial completion to determine that the work is proceeding generally in accordance with the technical submission.

(2) With the exception of exempt projects, construction phase services that constitute the practice of architecture must be performed by an architect, or under an architect's responsible control.

(3) If the architect, or the architect's firm, that stamped technical submissions to be used for construction of a non exempt project will not provide construction phase services described in OAR 806-010-0050(1), the architect must so advise the governmental authority that issued a permit for construction and the Board in writing within 10 days of when the architect becomes aware that they will not provide the construction phase services. This written notice must also include the project address and project owner’s name.

Statutory/Other Authority: ORS 670.310, 671.010 & 671.125
Statutes/Other Implemented: ORS 671.010 – 671.220/SB 224 (2023)
History:
BAE 3-2023, amend filed 10/10/2023, effective 01/02/2024
BAE 3-2019, amend filed 12/20/2019, effective 02/01/2020
BAE 2-2019, amend filed 04/10/2019, effective 05/01/2019
BAE 7-2014, f. & cert. ef. 10-23-14
BAE 3-2005, f. & cert. ef. 5-12-05
BAE 1-1999, f. & cert. ef. 3-25-99
AE 1-1996, f. 1-23-96, cert. ef. 2-1-96
AE 1-1981, f. & ef. 3-5-81
AE 1-1979, f. 5-31-79, ef. 6-1-79
AE 2-1978, f. & ef. 3-6-78
AE 6, f. 6-5-69
AE 5, f. 12-22-64


Please use this link to bookmark or link to this rule.